Brief from the customer

Backup our UK distribution centre. When the lights go out at one of our high street stores, we might have to turn our customers away. If we can’t restock the shelves at any of our stores throughout the region, they’ll walk away themselves, and might not come back! Evidently, this major retailer had considered the downstream effects of a mains supply failure at their distribution centre. Through their international electrical engineering arm, they asked JS Power to make sure the power kept running when the mains failed.

Location


United Kingdom

Equipment Provided


2 x 500kVA diesel generators
2 x Sound attenuation canopies – 75dBA @ 1m
2 x 11,000 litre external bunded fuel tank
Bunded pipework
Maintenance Contract

Solution

We supplied and installed a pair of 500kVA diesel generators to backup their distribution centre. We also added two 11,000 litre fuel tanks bunded according to DEFRA oil storage requirements, bunded pipework, and included a generator servicing contract. With 90% of current UK nuclear power stations to be decommissioned by 2023, and the new wave of nuclear power stations unlikely to fill the deficit in time, it looks increasingly unlikely that UK industry will face electricity supply difficulties. Armed with a pair of generators and JS Power’s maintenance regime, our clients will be in a position to cope with whatever the mains power supply throws at them, or doesn’t, in the future.

  • CE Marking
  • ISO 9001 registered
  • ISO 14001 registered
  • Safe Contractor Approved